Overview

Project Title

Cross Support Transfer Service--Tracking Data Service Issue 2

Approval

Approved

Document Number

922.2

Charter

3.06 Cross Support Transfer Services Working Group

Document Type

Blue

Description of Document

Update of CSTS Tracking Data Service to Issue 2 (B-2)

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

NASA

Book Editor Resources

1 MM

Prototype 1

Not Required

Prototype 1 Resources

Prototype 2

Not Required

Prototype 2 Resources

Prototype 3

Not Required

Prototype 3 Resources

Contribute

ESA

Monitor Only

CNES

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet12/1/202112/1/202112/1/2021
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet12/1/202212/1/202212/1/2022
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet2/1/20222/1/20222/1/2022
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet2/1/20222/1/2022
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet2/1/20222/1/2022
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet2/1/20222/1/2022
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/20223/1/20223/1/2022
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/20223/1/2022
First Agency ReviewMagenta BulletBlue Bullet4/1/20221/8/20221/8/2022
RID ResolutionMagenta BulletBlue Bullet5/1/20221/10/20221/10/2022
Secretariat Document Processing 2Magenta BulletBlue Bullet6/1/202211/1/202211/1/2022
Final Agency ReviewMagenta BulletBlue Bullet11/1/202211/1/2022
RID ResolutionMagenta BulletBlue Bullet11/1/202211/1/2022
First Prototype DevelopmentBlue Bullet11/1/202211/1/2022
Second Prototype DevelopmentBlue Bullet11/1/202211/1/2022
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet7/1/20221/12/20222/28/2023
Total Time to Complete
(in months)
-5
-10
Attachments
Version: 68.0
Created at 11/5/2021 4:48 AM by Holger Dreihahn
Last modified at 3/1/2023 11:28 AM by Brian Oliver