Overview

Project Title

Delta-DOR technical Characteristics and performance - Issue 2

Approval

Approved

Document Number

500.1

Charter

1.06 Delta-DOR Working Group

Document Type

Green

Description of Document

Issue 2 of the Delta-DOR Green Book addresses the following points on top of the current material: - Different signal structures that can be used for Deep Space and/or Near Earth Astrometry mission applications. Such signal structures could be: a) the use of spread spetrum DOR signals, b) the use of high rate telemetry downlinks in place of DOR tones (for certain kind of missions) c) sweeping DOR tones - System level approach addressing onboard signal generation, ground station recording, and processing center correlation algorithms. The book provides material that could evolve into a new Magenta Book for the recommendations on architectures and into a new Blue Book for the specific signal structures to be employed (to be issued with the RF&Mod WG)

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

N/A

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

NASA

Book Editor Resources

NASA/JPL (Project allocation: 6MM)

Prototype 1

Not Required

Prototype 1 Resources

Prototype 2

Not Required

Prototype 2 Resources

Prototype 3

Prototype 3 Resources

Contribute

ESA, JAXA

Monitor Only

FSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet10/31/201310/31/201312/3/2013CMC-P-2013-11-003 +DLR confirmation
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet12/3/201312/3/201312/3/2013
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet2/28/20152/28/20162/28/2016
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet4/30/20154/30/20164/30/2016
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet12/31/201512/31/201612/31/2016
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/20163/15/20173/15/2017
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet6/30/20166/30/20176/30/2017
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet8/31/201612/31/201911/30/2019
First Agency ReviewMagenta BulletBlue Bullet11/30/201911/30/2019
RID ResolutionMagenta BulletBlue Bullet11/30/201911/30/2019
Secretariat Document Processing 2Magenta BulletBlue Bullet11/30/201911/30/2019
Final Agency ReviewMagenta BulletBlue Bullet11/30/201911/30/2019
RID ResolutionMagenta BulletBlue Bullet11/30/201911/30/2019
First Prototype DevelopmentBlue Bullet11/30/201911/30/2019
Second Prototype DevelopmentBlue Bullet11/30/201911/30/2019
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet10/31/201612/31/201911/30/2019
Total Time to Complete
(in months)
34
72
Attachments
Version: 408.0
Created at 9/27/2013 2:26 AM by Madde Roberto
Last modified at 12/4/2019 8:40 AM by Brian Oliver