Overview

Project Title

TM Channel Coding for SCCC, Green Book

Approval

Approved

Document Number

130.11

Charter

5.02 Space Link Coding and Synchronization Working Group

Document Type

Green

Description of Document

The objective of this project is to complement the TM Channel Coding Green Book with an additional book (stand-alone document) to reflect the addition of SCCC (131.2-B) to the TM Coding options.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

SCCC-related patents exist but they are not affecting the Green Book

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

4 man months. Book editor Massimo Bertinelli (ESA).

Prototype 1

Not Required

Prototype 1 Resources

Not required

Prototype 2

Not Required

Prototype 2 Resources

Not required

Prototype 3

Prototype 3 Resources

Contribute

Monitor Only

CNES, DLR, FSA, NASA, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet1/31/20131/31/201312/22/2012CMC Resolution: CMC-R-2012-12-005
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet12/22/201212/22/201212/22/2012
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet3/30/20132/16/20182/16/2018Draft to be circulated before Spring 2018 meeting
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet9/30/20134/13/20187/2/2018
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet11/30/20136/15/20187/4/2018
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet3/30/20149/14/20188/30/2018
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet6/30/201410/12/20189/10/2018
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet10/30/20143/29/20193/29/2019
First Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet12/31/20145/31/20194/30/2019
Total Time to Complete
(in months)
24
76
Attachments
Version: 752.0
Created at 12/6/2012 10:18 AM by Bertinelli Massimo
Last modified at 5/1/2019 5:32 PM by Brian Oliver