Overview

Project Title

Cross-Support Specification Framework

Approval

Approved

Document Number

921.1

Charter

3.06 Cross Support Transfer Services Working Group

Document Type

Blue

Description of Document

The purpose of this Recommended Standard is to define the various logical components also known within this Recommended Standard  as procedures that are required for specifying Cross Support Transfer Services

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

ESA

Prototype 1

ESA

Prototype 1 Resources

ESA-NASA

Prototype 2

NASA

Prototype 2 Resources

ESA/CNES-NASA

Prototype 3

Prototype 3 Resources

Contribute

CNES, DLR

Monitor Only

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet11/14/2004
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet11/14/2004
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet9/29/2008
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet10/13/2008
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet11/28/2008
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet12/10/2008
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet1/15/2009
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet2/2/2009
First Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentOrange BulletBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet10/15/2010
Total Time to Complete
(in months)
70
Attachments
Version: 224.0
Created at 10/21/2008 3:33 AM by Doat Yves
Last modified at 5/3/2017 10:00 AM by Margherita di Giulio