Overview

Project Title

Bundle Protocol for CCSDS (was DTN Protocol)

Approval

Approved

Document Number

734.2

Charter

6.09 Delay Tolerant Networking Working Group

Document Type

Blue

Description of Document

<div>Protocol specification for an internetworking protocol suitable for space communication.</div>

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

NASA

Book Editor Resources

Lee Pitts (for NASA)

Prototype 1

Other

Prototype 1 Resources

An enhanced version of the DTN2 BP implementation from the Internet Research Task Force dtnrg. The NASA Space DTN Project has been maintaining the DTN2 implementation compatible with the BP-for-CCSDS Spec.

Prototype 2

NASA

Prototype 2 Resources

NASA will provide the ION Open Source (IOS) implementation.

Prototype 3

Prototype 3 Resources

Contribute

UKSA

Monitor Only

CSA, DLR, INPE, JAXA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/2008
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/2008
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/2009Slipped from 10/15/2008
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet4/15/2009
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet9/15/2009Slipped from 3/15/2009
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet10/15/2009
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/2010
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/2010
First Agency ReviewMagenta BulletBlue Bullet5/15/2010
RID ResolutionMagenta BulletBlue Bullet6/15/2010
Secretariat Document Processing 2Magenta BulletBlue Bullet8/15/2010
Final Agency ReviewMagenta BulletBlue Bullet9/15/2010
RID ResolutionMagenta BulletBlue Bullet10/15/2010
First Prototype DevelopmentBlue Bullet3/15/2011Begin development / adopt existing implementation
Second Prototype DevelopmentBlue Bullet3/15/2011Begin development / adopt existing implementation
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/2011CMC Poll Approval
Total Time to Complete
(in months)
36
Attachments
Version: 224.0
Created at 9/24/2008 12:56 PM by Scott Keith
Last modified at 10/9/2015 7:34 AM by Peccia Nestor