Overview

Project Title

USLP Blue Book Revisions 3.0

Approval

Approved

Document Number

732.1-B

Charter

5.04 Space Link Protocols Working Group

Document Type

Blue

Description of Document

Upon editing IPoC to add USLP, I noticed that USLP requires 2 more services, VC Packet and VC Access. These must be added to the document. Change maximum number of frames per CLTU from one to greater than one to match TC. Also add in security section table, diagram, and text concerning the order of COP to SDLS similar to TC to this book.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

N/A

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

N/A

Resources

Book Editor

NASA

Book Editor Resources

.1 FTE

Prototype 1

Not Required

Prototype 1 Resources

N/A Because similar service already exists higher up - MAP Service and MAP Access Service

Prototype 2

Not Required

Prototype 2 Resources

Prototype 3

Not Required

Prototype 3 Resources

Contribute

ESA, NASA, UKSA

Monitor Only

CNES, DLR

Resource Comments

N/A

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet9/5/2022Project was inadvertently not submitted for processing in CWE.
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet9/5/2022
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet9/5/2022
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet9/26/2022
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet10/31/2022
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet11/14/2022
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet11/21/2022The WG is on 12 May 2023 at this milestone.
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet12/19/2022
First Agency ReviewMagenta BulletBlue Bullet1/9/2023
RID ResolutionMagenta BulletBlue Bullet3/6/2023
Secretariat Document Processing 2Magenta BulletBlue Bullet3/20/2023
Final Agency ReviewMagenta BulletBlue Bullet4/10/2023
RID ResolutionMagenta BulletBlue Bullet5/8/2023
First Prototype DevelopmentBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet7/17/2023
Total Time to Complete
(in months)
10
Attachments
Version: 53.0
Created at 8/5/2022 1:27 PM by Greg Kazz
Last modified at 11/1/2023 1:50 PM by Greg Kazz