Overview

Project Title

Cross Support Transfer Services--Monitored Data Service Issue 2

Approval

Approved

Document Number

922.1

Charter

3.06 Cross Support Transfer Services Working Group

Document Type

Blue

Description of Document

Update of Blue Book to Issue 2 (B-2)

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

NASA

Book Editor Resources

1 MM

Prototype 1

Not Required

Prototype 1 Resources

Prototype 2

Not Required

Prototype 2 Resources

Prototype 3

Not Required

Prototype 3 Resources

Contribute

ESA

Monitor Only

CNES

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet12/1/2021
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet11/1/2021
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet1/1/2022
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/2022
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet
First Agency ReviewMagenta BulletBlue Bullet4/1/2022
RID ResolutionMagenta BulletBlue Bullet5/1/2022
Secretariat Document Processing 2Magenta BulletBlue Bullet6/1/2022
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentOrange BulletBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet7/1/2022
Total Time to Complete
(in months)
8