Overview

Project Title

Proximity-1 Coding & Synchronization Sublayer Modification to support USLP Frame Format

Approval

Approved

Document Number

211.2

Charter

5.02 Space Link Coding and Synchronization Working Group

Document Type

Blue

Description of Document

Modification of CCSDS 211.2-B-2 Proximity-1 Coding & Synchronization Sublayer to enable the additional use of the Version 4 transfer frame i.e., USLP transfer frame over the Proximity-1 Space Link.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

No new patent involved in this update.

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

This project is dependent upon the work being done by the SLP WG on the USLP Blue Book Project, in which the format of the USLP transfer frame is being defined.

Resources

Book Editor

NASA

Book Editor Resources

0.1 full time equivalent for duration of project.

Prototype 1

NASA

Prototype 1 Resources

0.1 full time equivalent for duration of testing - test procedure for this project has already been written and agreed to.

Prototype 2

DLR

Prototype 2 Resources

0.1 full time equivalent for duration of testing test procedure for this project has already been written and agreed to.

Prototype 3

Prototype 3 Resources

Contribute

DLR, NASA

Monitor Only

ESA, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet4/2/2018CMC-P-2018-04-001 closed 17 April 2018
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet4/12/2018
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet6/15/2018
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet7/15/2018
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet8/15/2018
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet9/19/2016
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet11/14/2018
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet12/12/2018CMC-P-2019-02-004 approved to Angecy review Start
First Agency ReviewMagenta BulletBlue Bullet1/25/2019Agency Review end date fixed for 3 May 2019
RID ResolutionMagenta BulletBlue Bullet2/22/2019At Spring 2019 Meeting
Secretariat Document Processing 2Magenta BulletBlue Bullet3/21/2019No extra review
Final Agency ReviewMagenta BulletBlue Bullet3/28/2019No extra review
RID ResolutionMagenta BulletBlue Bullet4/10/2019No extra review
First Prototype DevelopmentOrange BulletBlue Bullet9/26/2019USLP Prototypes available
Second Prototype DevelopmentBlue Bullet3/8/2019USLP Prototypes available
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet7/24/2019
Total Time to Complete
(in months)
15
Attachments
Version: 190.0
Created at 4/10/2016 6:39 PM by CCSDS Tech Support
Last modified at 11/21/2019 10:52 AM by Brian Oliver