Overview

Project Title

Space Data Link Security (SDLS) protocol : extended procedures

Approval

Approved

Document Number

355.1

Charter

5.09 Space Data Link Security WG

Document Type

Blue

Description of Document

"Space Data Link Security (SDLS) protocol : extended procedures" BB will complement "SDLS core protocol" BB currently being finalized by SDLS WG. It will specify SDLS management functions which are needed to interoperate in non static configuration scenarios : - Security Association (SA) management - Key management including in flight rekeying (OTAR) - Monitoring & control of the on-board SDLS protocol Those functions correspond to protocol development effort build-2 as defined in approved SDLS WG charter.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

Daniel Fischer - ESA

Prototype 1

CNES

Prototype 1 Resources

CNES

Prototype 2

ESA

Prototype 2 Resources

The prototype provider has not been identified yet.

Prototype 3

Prototype 3 Resources

Contribute

CNES, DLR, ESA, NASA

Monitor Only

FSA, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet11/17/2011
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet11/17/2011
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet4/15/2012
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet6/15/2012
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet9/15/2012
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet11/15/2012
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet1/15/2013
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/2013CMC Poll CMC-P-2018-05-009
First Agency ReviewMagenta BulletBlue Bullet5/15/2013Closing date for RED-1 Agency review
RID ResolutionMagenta BulletBlue Bullet7/15/2013RID disposition performed at Fall 2018 meeting
Secretariat Document Processing 2Magenta BulletBlue Bullet8/15/2013No extra Agency review
Final Agency ReviewMagenta BulletBlue Bullet10/15/2013No extra Agency review
RID ResolutionMagenta BulletBlue Bullet11/15/2013No extra Agency review
First Prototype DevelopmentOrange BulletBlue Bullet8/15/2013
Second Prototype DevelopmentBlue Bullet10/15/2013
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet12/15/2013
Total Time to Complete
(in months)
25
Attachments
Version: 650.0
Created at 10/11/2011 1:47 PM by Moury Gilles
Last modified at 3/1/2020 2:05 PM by Laura Stafford