Overview

Project Title

Proximity-1 Space Link Protocol—Data Link Layer - Issue 5

Approval

Approved

Document Number

211.0

Charter

5.04 Space Link Protocols Working Group

Document Type

Blue

Description of Document

When the following CCSDS Link Layer documents are due for their mandatory 5-year review. Note - the review of each document depends upon the last issue date. The document under current review is the Prox-1 Space Data Link protocol (the C&S WG is also reviewing the Sync and channel Prox-1 book.) The RF&Mod WG is reviewing simultaneously the prox-1 Physical layer.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

There are no patents envisioned in this WG

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

NASA

Book Editor Resources

Heavy Technical work of reviewing and updating the document has taken place. Next effort involves resolving RIDs (anticipated to be around 10 or so) from the current agency review and making appropriate changes to document concurred by WG. Level of effort is .1 FTE from July 2012 to Nov 2013.

Prototype 1

Not Required

Prototype 1 Resources

NASA has already implemented Proximity-1 in CE 505 and Electra transceivers. This project is adding no new feature requiring prototypes.

Prototype 2

Not Required

Prototype 2 Resources

ESA has already implemented Proximity-1 in Melecom transceiver. This project is adding no new feature requiring prototypes.

Prototype 3

Prototype 3 Resources

Contribute

ESA, NASA, UKSA

Monitor Only

CNES, ESA, NASA, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet12/15/2009
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet12/15/2009
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet4/15/2010
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet4/26/2010
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet6/15/2010
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet8/30/2010
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet9/15/2010Pink Book
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet9/30/2010Agency review started on 19 March 2012, ending 1 June 2012
First Agency ReviewMagenta BulletBlue Bullet10/15/2010RIDs collected
RID ResolutionMagenta BulletBlue Bullet12/15/2010Delayed by discussion on (P)ICS
Secretariat Document Processing 2Magenta BulletBlue Bullet1/15/2011CESG-P-2013-11-006
Final Agency ReviewMagenta BulletBlue Bullet2/1/2011NOT needed
RID ResolutionMagenta BulletBlue Bullet3/1/2011NOT needed
First Prototype DevelopmentOrange BulletBlue Bullet12/1/2010NOT neeeded. No new features.
Second Prototype DevelopmentBlue Bullet5/1/2011NOT neeeded. No new features.
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet5/1/2011CMC-P-2013-12-005 APPROVED
Total Time to Complete
(in months)
16