Overview

Project Title

Mission Operations - Common Services

Approval

Approved

Document Number

522.0

Charter

2.04 Spacecraft Monitoring and Control Working Group

Document Type

Blue

Description of Document

It provides a common service infrastructure for all Mission Operations services.  This ensures a common approach, simplifies the task of implementing each Mission Operations service, and isolates the Mission Operations service layer from the underlying implementation technology.  The layer is comprised of common service elements used by all Mission Operations services that are directly exposed to mission operations applications (e.g., the Service Directory).

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

Prototype 1

ESA

Prototype 1 Resources

Prototype 2

CNES

Prototype 2 Resources

Prototype 3

Prototype 3 Resources

Contribute

DLR, NASA, UKSA

Monitor Only

ASI, CSA, FSA, INPE, JAXA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet1/1/2006This is mainly a re-arrangement of existing material following the SM&C document reorganisation documented in the SM&C document Roadmap.
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet1/1/2006
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet6/2/2009The WG has substantially reworked the concepts behind the COMMON services in order to align it with the updates done the MAL and COM.
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet6/30/2009
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet6/30/2009
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet6/30/2009
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet7/3/2009
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet7/6/2009
First Agency ReviewMagenta BulletBlue Bullet8/17/2009
RID ResolutionMagenta BulletBlue Bullet10/30/2009
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentBlue Bullet10/30/2009
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet12/15/2009
Total Time to Complete
(in months)
47
Attachments
Version: 757.0
Created at 11/23/2008 8:46 AM by Merri Mario
Last modified at 5/28/2020 3:22 PM by Laura Stafford