Overview

Project Title

Open Archive Information Systems Interoperability Framework (OAIS-IF) Architecture Definition

Approval

Approved

Document Number

671.0

Charter

2.01 Data Archive Interoperability Working Group

Document Type

Magenta

Description of Document

The purpose of this recommendation is to provide a standard reference architecture that encompasses the capture, management, access, and exchange of information and its long-term preservation in an archive. The intent is that this recommendation will be applicable to the entire information lifecycle and in all environments (including the Space environment - both flight and ground systems).

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

There is no current standard, but there are possible items that can feed into this project. EU LTDP project and individual Space Agencies may have materials that may directly address some portions of this standard. There are several CCSDS architectures that may inform our architectural work. See MOIMS-DAI Report to CMC for information organizations surveyed and related standards available from those organizations.

Resources

Book Editor

NASA

Book Editor Resources

6mm approved NASA/JPL funding (but source is not typical SCaN funding)

Prototype 1

Prototype 1 Resources

1 mm

Prototype 2

Prototype 2 Resources

1 mm

Prototype 3

Prototype 3 Resources

Contribute

CNES, DLR, ESA, NASA, UKSA

Monitor Only

CNES, DLR, NASA, UKSA

Resource Comments

Industry Resources outside the normal Space Agency funding paths are being made available to support this project. UKSA (Giaretta Associates) NASA (JPL, SEDAC, Kearney Solutions, Garrett Software) NARA (CCSDS liaison organization) is also contributing. Others (non-space agencies) are also contributing

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet7/1/20177/1/20177/28/2017
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet7/15/20177/15/20177/31/2017
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet2/4/20181/4/20189/1/2018
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet4/6/20184/6/201810/19/2018
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet6/20/20183/31/20233/15/2023
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet8/20/20184/30/20234/26/2023
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet10/20/20184/1/2025
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/20196/1/2025
First Agency ReviewMagenta BulletBlue Bullet10/29/201910/1/2025Concurrent with ISO DIS review (12 weeks)
RID ResolutionMagenta BulletBlue Bullet5/16/20201/1/2026
Secretariat Document Processing 2Magenta BulletBlue Bullet8/18/20202/2/2026
Final Agency ReviewMagenta BulletBlue Bullet3/19/20216/1/2026Concurrent with ISO FDIS review (3 month)
RID ResolutionMagenta BulletBlue Bullet5/19/202110/1/2026
First Prototype DevelopmentOrange BulletBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet9/25/202112/1/2026
Total Time to Complete
(in months)
50
111
Attachments
Version: 418.0
Created at 1/26/2017 7:03 PM by Garrett John
Last modified at 11/6/2024 9:10 AM by John Garrett