Overview

Project Title

Simultaneous Transmission of GMSK Telemetry and PN Ranging

Approval

Approved

Document Number

413.1

Charter

5.01 RF and Modulation Working Group

Document Type

Green

Description of Document

This Green Book supports CCSDS recommendations 401(2.4.22A), and 401(2.4.22B) addressing the use of spacecraft telemetry bandwidth-efficient modulations with simultaneous ranging.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

None

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

Enrico Vassallo, ESA - 4mm

Prototype 1

Not Required

Prototype 1 Resources

Prototype 2

Not Required

Prototype 2 Resources

Prototype 3

Prototype 3 Resources

Contribute

NASA

Monitor Only

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet4/6/20144/6/20144/2/2014Approved CMC Poll
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet4/2/20144/2/20144/2/2014
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet3/20/20143/20/20143/20/2014For Spring 14 Meeting
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet6/15/20146/15/20146/15/2014After Spring 14 Meeting
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet10/15/20143/15/20163/21/2016Before Spring 16 Meeting
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet3/30/20154/30/20165/10/2016
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet5/30/20156/30/20166/27/2016
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet10/1/20155/1/20175/1/2017i.e. start of CESG Poll for Publication
First Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet12/31/20155/30/20175/30/2017Includes Final Secretariat Document Processing + CESG Poll + CMC Poll for PUBLICATION
Total Time to Complete
(in months)
21
37
Attachments
Version: 348.0
Created at 3/20/2014 2:46 AM by Calzolari Gian Paolo
Last modified at 5/30/2017 12:13 PM by Brian Oliver