Schedule Milestones | | | | | Original Completion Date (Date in M/D/YYYY format.) | Estimated Completion Date (Date in M/D/YYYY format.) | Actual Completion Date (Date in M/D/YYYY format.) | Comments (Date in M/D/YYYY format.) |
Project Approved | | | | | 5/10/2004 | 5/10/2004 | 5/10/2004 | Date of first meetings where plan established. XML representations mandated by CMC somewhat earlier. |
Project Start Date | | | | | | | | |
Internal WG Review | | | | | | | | |
First Draft Circulated to WG | | | | | 8/30/2004 | 8/30/2004 | 8/30/2004 | |
First Draft Comments Due | | | | | 11/15/2004 | 11/15/2004 | 11/15/2004 | |
Second draft circulated to WG | | | | | 9/2/2005 | 9/2/2005 | 9/2/2005 | Actually seventh draft, just prior to first Red Book |
Second Draft Comments Due | | | | | 9/12/2005 | 9/12/2005 | 9/12/2005 | Date of Fall Meetings 2005 |
Final WB Submitted to AD for Further Processing | | | | | 10/17/2005 | 10/17/2005 | 10/17/2005 | White book 8th draft submitted to Secretariat |
External Milestones | | | | | | | | |
Secretariat Document Processing | | | | | 1/13/2006 | 1/13/2006 | 1/13/2006 | Date of announcement of first Agency Review opportunity |
First Agency Review | | | | | 3/30/2006 | 3/30/2006 | 3/30/2006 | End date of first Agency Review |
RID Resolution | | | | | 9/30/2007 | 3/31/2009 | 1/20/2009 | Draft R1.2 resolved all RIDs from first Agency Review |
Secretariat Document Processing 2 | | | | | 4/30/2009 | 6/30/2009 | 6/17/2009 | Planned after Spring 2009 Meetings |
Final Agency Review | | | | | 9/30/2009 | 10/15/2009 | 9/1/2009 | Assumes 2 month Secretariat processing, 3 month review |
RID Resolution | | | | | 11/30/2009 | 1/31/2010 | 11/22/2009 | RID updated doc sent to Secretariat 11/22/2009 |
First Prototype Development | | | | | 11/30/2009 | 5/15/2010 | 2/28/2010 | |
Second Prototype Development | | | | | 11/30/2009 | 10/1/2010 | 10/27/2010 | |
CMC Approval | | | | | 12/31/2009 | 12/31/2010 | 12/16/2010 | Results of CMC poll CMC-P-2010-11-005 beginning 24 November 2010 and ending 15 December 2010 |
Total Time to Complete (in months) | | | | | 1,298 | 1,310 | | |