Project Title

USLP Green Book Version 2

Approval

Approved

Document Number

700.1

Charter

5.04 Space Link Protocols Working Group

Document Type

Green

Description of Document

The SLP WG has been collecting updates to the version 1 Green book and has accumulated a number of changes to warrant the release of a new version. These changes include to a great extent but are not limitied to: o limit the Frame Error Control Field options to CRC-16 (i.e. removing CRC-32 option), o clarify the way USLP interfaced to TC Coding Layer, o clarify options about USLP Truncated transfer Frames, o clarify applicability of COP-1 and COP-P, o clarify usage of AD and BD Frames when COP-1 is applied

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

None

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

None

Resources

Book Editor

NASA

Book Editor Resources

0.1 FTE

Prototype 1

Not Required

Prototype 1 Resources

N/A

Prototype 2

Not Required

Prototype 2 Resources

N/A

Prototype 3

Not Required

Prototype 3 Resources

N/A

Contribute

ESA, NASA, UKSA

Monitor Only

CNES, DLR

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet11/15/202011/15/202012/9/2020CMC-P-2020-11-003
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet11/22/202011/22/202012/9/2020
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet2/16/20212/16/20212/16/2021
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/20213/15/20213/15/2021
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet7/15/20219/15/20219/15/2021
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet9/15/202111/15/202111/15/2021
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet11/15/20219/15/2025
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet1/15/202212/1/2025
First Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentOrange BulletBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/20222/1/2026
Total Time to Complete
(in months)
15
61
Attachments
Version: 195.0
Created at 10/30/2020 11:51 AM by Greg Kazz