Overview

Project Title

Space link protocols over ETSI DVB-S2 standard, Issue 2

Approval

Approved

Document Number

131.3

Charter

5.02 Space Link Coding and Synchronization Working Group

Document Type

Blue

Description of Document

This update to the Blue Book will produce issue 2, enabling the use USLP frames as well as allowing space-to-space and ground-to-space links applications.

Applicable Patents

There are patent issues in this work area, but appropriate ISO forms have been submitted indicating RAND licensing policy by the patent holder or licensor (explain in comments).

Patent Comments

Same as 131.3-B-1. Up to now no new patent identified.

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

CNES

Book Editor Resources

Total resources: 2 work-months, by CNES. Nominal time from other Working Group members to review the document. Lead editors: CNES.

Prototype 1

Not Required

Prototype 1 Resources

Prototype NOT required.

Prototype 2

Not Required

Prototype 2 Resources

Prototype NOT required.

Prototype 3

Not Required

Prototype 3 Resources

Contribute

CNES

Monitor Only

DLR, ESA, NASA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet7/30/20197/30/20197/22/2019CMC E-Poll CMC-P-2019-07-002
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet8/1/20199/1/20199/1/2019
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet8/20/20199/30/201910/20/2019Before Fall 19 Meeting
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet9/30/201910/30/201910/27/2019After Fall 19 Meeting
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet10/15/201911/15/201910/28/2019
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet11/15/201911/30/201910/30/2019After Fall 19 Meeting
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet11/30/201912/30/201910/31/2019
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet1/15/20205/15/20214/21/2021Agency REview started 21 April 2021
First Agency ReviewMagenta BulletBlue Bullet3/15/20207/15/20217/7/2021
RID ResolutionMagenta BulletBlue Bullet5/15/202010/15/20217/7/2021By Fall 21 Meeting
Secretariat Document Processing 2Magenta BulletBlue Bullet6/15/202012/15/20213/30/2022
Final Agency ReviewMagenta BulletBlue Bullet6/15/202012/15/20213/30/2022Not expected
RID ResolutionMagenta BulletBlue Bullet6/15/202012/15/20213/30/2022Not expected
First Prototype DevelopmentBlue Bullet6/15/202012/15/20213/30/2022Not required
Second Prototype DevelopmentBlue Bullet6/15/202012/15/20213/30/2022Not required
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet10/15/20204/15/20223/30/2022Includes CESG Poll + CMC Poll for PUBLICATION
Total Time to Complete
(in months)
14
31
Attachments
Version: 189.0
Created at 6/28/2019 8:27 AM by Gian Paolo Calzolari
Last modified at 5/2/2022 10:15 AM by Brian Oliver