Overview

Project Title

“TM Synchronization and Channel Coding”, New channel interleaver for TURBO encoder

Approval

Approved

Document Number

131.0

Charter

5.02 Space Link Coding and Synchronization Working Group

Document Type

Blue

Description of Document

This update to the Blue Book will produce a new issue introducing an optional channel interleaver to be applied at the output of the TURBO encoder

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

N/A

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

N/A

Resources

Book Editor

NASA

Book Editor Resources

4 work-months. Lead editor: NASA.

Prototype 1

NASA

Prototype 1 Resources

NASA 2 Work Months

Prototype 2

ESA

Prototype 2 Resources

ESA 2 Work Months

Prototype 3

Not Required

Prototype 3 Resources

Contribute

ESA, NASA

Monitor Only

CNES, DLR

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet7/30/20197/30/20197/22/2019CMC E-Poll CMC-P-2019-07-002
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet8/1/201910/1/202010/1/2020completed
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet10/30/20195/14/20215/27/2021completed
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet11/30/20196/13/20215/27/2021
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet1/30/202010/19/20234/29/2024
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet2/28/202011/5/20234/29/2024
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet4/30/20206/1/202411/6/2024
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet5/30/202012/1/2024
First Agency ReviewMagenta BulletBlue Bullet7/30/20202/1/2025
RID ResolutionMagenta BulletBlue Bullet9/30/20205/1/2025
Secretariat Document Processing 2Magenta BulletBlue Bullet10/30/2020
Final Agency ReviewMagenta BulletBlue Bullet10/30/2020Not expected
RID ResolutionMagenta BulletBlue Bullet10/30/2020Not expected
First Prototype DevelopmentOrange BulletBlue Bullet11/30/20204/29/20244/29/2024
Second Prototype DevelopmentBlue Bullet11/30/20204/29/20244/29/2024
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet1/15/20211/15/2025Includes CESG Poll + CMC Poll for PUBLICATION
Total Time to Complete
(in months)
17
51
Attachments
Version: 364.0
Created at 6/17/2019 5:03 AM by Gian Paolo Calzolari
Last modified at 11/6/2024 11:18 AM by Andrea Modenini