Overivew

Project Title

Proximity-1 Space Link Protocol - Data Link Layer (Issue6)

Approval

Approved

Project Status

On Schedule

Project Phase

Second draft circulated to WG

Document Number

211.0

Charter

5.04 Space Link Protocols Working Group

Document Type

Blue

Description of Document

The CCSDS Recommended Standard for Proximity-1 Space Link Protocol—Data Link Layer specifies the protocol, services, and procedures pertaining to the CCSDS Version-3 Transfer Frame. Issue 6 of this Recommended Standard will include in "Proximity-1 protocol suite the possibility of using either Version-3 or Version-4 (USLP) Transfer Frames on top of Proximity-1 Coding and Synchronization Sublayer & Proximity-1 Physical Layer.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

N/A

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

N/A

Resources

Book Editor

NASA

Book Editor Resources

.1 FTE provided by NASA

Prototype 1

NASA

Prototype 1 Resources

Prototypes already developed for 732.1-B validates this new issue.

Prototype 2

DLR

Prototype 2 Resources

Prototypes already developed for 732.1-B validates this new issue.

Prototype 3

Prototype 3 Resources

Contribute

DLR, ESA, NASA

Monitor Only

CNES, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet5/1/20195/1/20194/26/2019CMC-P-2019-04-005 completed 26 April 2019
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet5/2/20195/2/20195/2/2019
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet5/3/20195/3/20195/3/2019Input to Spring 2019 Meeting
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet5/4/20195/7/20195/7/2019Discussed at Spring 2019 Meeting
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet9/15/20199/15/2019
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet10/15/201910/15/2019Before Fall 2019 Meeting
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet11/30/201911/30/2019
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet2/15/20202/15/2020
First Agency ReviewMagenta BulletBlue Bullet4/15/20204/15/2020
RID ResolutionMagenta BulletBlue Bullet5/30/20205/30/2020
Secretariat Document Processing 2Magenta BulletBlue Bullet6/15/20206/15/2020Second Agency Review not envisaged
Final Agency ReviewMagenta BulletBlue Bullet9/15/20209/15/2020
RID ResolutionMagenta BulletBlue Bullet10/30/202010/30/2020
First Prototype DevelopmentBlue Bullet4/16/20194/16/2019Already available from ULSP Project
First Prototype DevelopmentBlue Bullet4/16/20194/16/2019Already available from ULSP Project
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet2/15/20212/15/2021
Total Time to Complete
(in months)
21
21
Attachments