Overview

Project Title

CSTS Specification Framework - Update

Approval

Approved

Document Number

921.1

Charter

3.06 Cross Support Transfer Services Working Group

Document Type

Blue

Description of Document

Updates needed to the CSTS Specification Framework (SFW) for supporting Forward Frame CSTS. This is a pink sheet/pink book update project. Per 2018 Spring Meetings and as noted during CESG report to CMC, prototyping for frame work updates will be covered by FF-CSTS prototyping.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

1 WM

Prototype 1

NASA

Prototype 1 Resources

1 WM (Note this is essentially already covered under prototype resources for FF-CSTS, as FF-CSTS is driving the updates for the CSTS Framework)

Prototype 2

NASA

Prototype 2 Resources

1 WM (Note this is essentially already covered under prototype resources for FF-CSTS, as FF-CSTS is driving the updates for the CSTS Framework)

Prototype 3

Prototype 3 Resources

Contribute

ESA

Monitor Only

ESA, NASA

Resource Comments

Resources are minimal; per Spring 2018 meetings, prototyping effort is to be combined with FF-CSTS prototyping.

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet11/12/201811/12/201811/12/2018
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet11/12/201811/12/201811/12/2018
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet11/12/201811/12/201811/12/2018Notes were kept by WG during FF-CSTS notes; well known what is required
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet11/12/201811/12/201811/12/2018
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet11/12/201811/12/201811/12/2018
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet11/12/201811/12/201811/12/2018
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet11/12/201811/12/201811/12/2018
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet1/15/20191/15/20191/15/2019
First Agency ReviewMagenta BulletBlue Bullet4/9/20194/9/20194/9/2019
RID ResolutionMagenta BulletBlue Bullet4/15/20194/15/20194/15/2019
Secretariat Document Processing 2Magenta BulletBlue Bullet6/15/20196/15/20196/15/2019
Final Agency ReviewMagenta BulletBlue Bullet8/15/20198/15/20198/15/2019
RID ResolutionMagenta BulletBlue Bullet9/15/20199/15/20199/15/2019
First Prototype DevelopmentBlue Bullet7/15/201912/31/20194/27/2020
Second Prototype DevelopmentBlue Bullet7/15/201912/31/20194/27/2020
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet10/30/20199/30/20203/1/2021
Total Time to Complete
(in months)
11
22
Attachments
Version: 279.0
Created at 10/23/2018 5:40 AM by Erik Barkley
Last modified at 3/2/2021 11:21 AM by Laura Stafford