Project Title

Proximity-1 Space Link Protocol—Physical Layer, Issue 4

Approval

Approved

Project Status

All Tasks Completed

Project Phase

Project Completed

Document Number

211.1

Charter

5.01 RF and Modulation Working Group

Document Type

Blue

Description of Document

The CCSDS Recommended Standard for Proximity-1 Space Link Protocol--Data Link Layer specifies the protocol, services, and procedures pertaining to the CCSDS Version-3 Transfer Frame. This project will update the current CCSDS 211.1-B-3 Proximity-1 Space Link Protocol—Physical Layer. Blue Book. Issue 3. March 2006.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

N/A

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

ESA

Prototype 1

Not Required

Prototype 1 Resources

Not Required. This review does not intruduce new features and then there is no need for prototypes.

Prototype 2

Not Required

Prototype 2 Resources

Not Required. This review does not intruduce new features and then there is no need for prototypes.

Prototype 3

Prototype 3 Resources

Contribute

ESA, FSA, NASA

Monitor Only

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet12/16/201112/16/201112/16/2011
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet12/16/201112/16/201112/16/2011
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet12/16/201112/16/201112/16/2011
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet12/16/201112/16/201112/16/2011
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet12/16/201112/16/201112/16/2011
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet12/16/201112/16/201112/16/2011
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet12/19/201112/19/201112/25/2011
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet1/31/20121/31/20123/19/2012Agency review started on 19 March 2012, ending 1 June 2012
First Agency ReviewMagenta BulletBlue Bullet3/31/20126/1/20126/1/2012
RID ResolutionMagenta BulletBlue Bullet4/30/201210/30/201210/18/2012
Secretariat Document Processing 2Magenta BulletBlue Bullet5/30/201212/15/201311/25/2013Delayed by discussion on (P)ICS; CESG-P-2013-11-007
Final Agency ReviewMagenta BulletBlue Bullet7/30/201212/15/201311/25/2013NOT needed
RID ResolutionMagenta BulletBlue Bullet9/30/201212/15/201311/25/2013NOT needed
First Prototype DevelopmentBlue Bullet9/30/201212/15/201311/25/2013NOT needed
First Prototype DevelopmentBlue Bullet9/30/201212/15/201311/25/2013NOT needed
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet10/30/20122/15/20141/6/2014CMC-P-2013-12-006 APPROVAL
Total Time to Complete
(in months)
10
26