Legend for Schedule Milestones
= Required for Orange Books
= Required for Green Books
= Required for Magenta Books
= Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books
Schedule Milestones | | | | | Original Completion Date (Date in M/D/YYYY format.) | Estimated Completion Date (Date in M/D/YYYY format.) | Actual Completion Date (Date in M/D/YYYY format.) | Comments (Date in M/D/YYYY format.) |
Project Approved | | | | | 5/11/2010 | 5/11/2010 | 5/7/2010 | Approved at SLS Plenary in Portsmouth |
Project Start Date | | | | | | | | |
Internal WG Review | | | | | | | | |
First Draft Circulated to WG | | | | | 5/11/2010 | 5/11/2010 | 5/4/2010 | First discussion @ Spring 2010 Meeting |
First Draft Comments Due | | | | | 7/1/2010 | 7/1/2010 | 5/31/2010 | Deadline set @ Spring 2010 Meeting |
Second draft circulated to WG | | | | | 9/15/2010 | 9/15/2010 | 6/18/2010 | Updated after comments |
Second Draft Comments Due | | | | | 10/10/2010 | 10/10/2010 | 10/27/2010 | Comments discussed @ Fall 2010 Meeting |
Final WB Submitted to AD for Further Processing | | | | | 12/1/2010 | 12/1/2010 | 10/30/2010 | Finalized at Fall 2010 Meeting for CESG Approval |
External Milestones | | | | | | | | |
Secretariat Document Processing | | | | | 1/15/2011 | 3/15/2011 | 3/21/2011 | Red Book on line for line for CCSDS Agency review |
First Agency Review | | | | | 3/15/2011 | 5/15/2011 | 4/29/2011 | Due date for receipt of Agency review comments expired 29 April 2011 |
RID Resolution | | | | | 5/1/2011 | 6/15/2011 | 6/15/2011 | Discussed @ Spring 2011 Meeting |
Secretariat Document Processing 2 | | | | | 5/15/2011 | 7/15/2011 | 6/15/2011 | Approval version submitted to CESG poll |
Final Agency Review | | | | | | | 6/15/2011 | Not needed - Finalized @ Spring 2011 Meeting |
RID Resolution | | | | | | | 6/15/2011 | Not needed - Finalized @ Spring 2011 Meeting |
First Prototype Development | | | | | | | | N/A |
Second Prototype Development | | | | | | | | N/A |
CMC Approval | | | | | 6/1/2011 | 8/1/2011 | 7/26/2011 | Published on CCSDS Website - CCSDS 131.4-M-1 |
Total Time to Complete (in months) | | | | | 1,315 | 1,317 | | |