Overivew

Project Title

Mission Operations - Mission Data Product Distribution Services

Approval

Approved

Project Status

On Schedule

Project Phase

First draft circulated to WG

Document Number

522.2

Charter

2.04 Spacecraft Monitoring and Control Working Group

Document Type

Blue

Description of Document

The Mission Data Product Distribution service supports the provision of mission data products. This includes:
- Batch Product Request (in a given format, e.g. zip): e.g. TM/TC Frames/Packets/Parameters; Mission products (e.g. pictures, reports); Auxiliary data
- Stream Product Request: Same as above
- Standing Order Request.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

6mm. The specification of MO bindings to a transport and encoding is not a complext conceptual matter but more a question of a mapping. The existing SPP blue book provides a good template for producing other binding specifications. However a major part of the work is already done in the context of a parallel ESA activity (outside CCSDS), which has produced a draft specification in the expected Blue Book format. Hence it is expected that 1mm of effort shall be needed in the WG for the review and finalisation of the book.

Prototype 1

ESA

Prototype 1 Resources

3mm In the context of the above mentioned ESA parallel activity a prototype will be implemented. Hence less effort is needed in the context of the CCSDS WG.

Prototype 2

CNES

Prototype 2 Resources

Prototype 3

Prototype 3 Resources

Contribute

DLR, FSA, NASA, UKSA

Monitor Only

JAXA

Resource Comments

See above points regarding the ESA parallel activity.

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet1/1/20063/31/20153/31/2015
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet1/1/20061/15/20161/1/2015
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet10/1/20101/15/201610/1/2015
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet10/22/20102/28/20161/31/2016
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet11/5/201010/19/201610/19/2016
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet11/26/201011/19/201611/19/2016
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet12/10/20103/21/20173/21/2017
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet12/17/201011/30/2018
First Agency ReviewMagenta BulletBlue Bullet2/8/2011
RID ResolutionMagenta BulletBlue Bullet5/23/2011
Secretariat Document Processing 2Magenta BulletBlue Bullet5/30/2011
Final Agency ReviewMagenta BulletBlue Bullet6/29/2011
RID ResolutionMagenta BulletBlue Bullet10/11/2011
First Prototype DevelopmentBlue Bullet2/8/2011
First Prototype DevelopmentBlue Bullet4/9/2011
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet10/25/201112/15/2019
Total Time to Complete
(in months)
69
46
Attachments
Version: 224.0
Created at 11/23/2008 9:22 AM by Merri Mario
Last modified at 10/18/2018 3:42 AM by Sam Cooper