Overview

Project Title

Device Virtualisation Service

Approval

Approved

Document Number

871.2

Charter

4.02 Application Support Services Working Group

Document Type

Magenta

Description of Document

A specification for a spacecraft command and data acquisition service that enables onboard applications to access virtualized onboard devices, and define the service interface used to access that service.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

None

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

UKSA

Book Editor Resources

Stuart Fowell

Prototype 1

Not Required

Prototype 1 Resources

N/A

Prototype 2

Not Required

Prototype 2 Resources

N/A

Prototype 3

Prototype 3 Resources

Contribute

ESA, NASA, UKSA

Monitor Only

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet10/3/200210/1/200210/1/2002
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet10/1/200210/1/200210/1/2002
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet10/5/200810/3/200810/3/2008
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet10/12/200810/10/200810/10/2008
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet3/31/20098/29/20112/28/2012
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet4/19/20099/27/20113/31/2012
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet5/31/20093/29/20124/11/2012
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet6/30/20093/29/20125/23/2012
First Agency ReviewMagenta BulletBlue Bullet10/31/200911/4/201311/8/2013
RID ResolutionMagenta BulletBlue Bullet3/31/20101/6/20141/27/2014
Secretariat Document Processing 2Magenta BulletBlue Bullet4/30/20102/3/20141/27/2014
Final Agency ReviewMagenta BulletBlue Bullet5/31/20103/3/20141/27/2014
RID ResolutionMagenta BulletBlue Bullet9/30/20104/7/20141/27/2014
First Prototype DevelopmentOrange BulletBlue Bullet5/31/2009
Second Prototype DevelopmentBlue Bullet5/31/2010
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet12/31/20105/5/20143/13/2014Approved by CMC Poll
Total Time to Complete
(in months)
97
137