Overview

Project Title

Service Management Operations Concept Book

Approval

Document Number

Charter

3.03 Cross Support Service Management Working Group

Document Type

Green

Description of Document

Concepts in relation to structuring of service management blue book; key operational concepts supported by service management blue book

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

None

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

Book Editor Resources

Prototype 1

Prototype 1 Resources

Prototype 2

Prototype 2 Resources

Prototype 3

Prototype 3 Resources

Contribute

Monitor Only

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet10/22/200810/22/200810/22/2008
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet12/10/200712/10/200712/10/2007
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet6/6/20086/6/20086/6/2008
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet11/20/200811/20/200811/20/2008
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet12/10/200812/10/20087/30/2009
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet1/20/200911/20/20093/21/2011
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet3/1/200912/30/20095/16/2011
First Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentOrange BulletBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet4/1/20091/15/20105/27/2011
Total Time to Complete
(in months)
1,290
1,299
Attachments
Version: 6295.0
Created at 3/31/2010 11:42 PM by CCSDS Tech Support