Overview

Project Title

Security Assessments for Space Systems

Approval

Draft

Document Number

Charter

1.02 Security Working Group

Document Type

Green

Description of Document

The intent for this project is to develop a Green Book which will provide information regarding quantification of security assessments against space systems. This will include assessment from Blue Team (capability to detect) and Red Team (offensive security technique) perspectives, the pedigree of such assessments, and the guidelines as to their conduct and findings reporting. This is well understood for terrestrial systems, but not for space systems which are also very concerned with system security.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

NIST RMF, ISO 27005, ISO 31000

Resources

Book Editor

NASA

Book Editor Resources

4mm

Prototype 1

Not Required

Prototype 1 Resources

Prototype 2

Not Required

Prototype 2 Resources

Prototype 3

Not Required

Prototype 3 Resources

Contribute

ESA

Monitor Only

CNES, DLR, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet2/3/2025
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet2/24/2025
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet5/30/2025
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet9/1/2025
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet12/1/2025
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet2/2/2026
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet5/4/2026
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet6/15/2026
First Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentOrange BulletBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet9/21/2026
Total Time to Complete
(in months)
19
Attachments
Version: 39.0
Created at 11/29/2024 11:54 AM by Howard Weiss
Last modified at 12/13/2024 11:49 AM by Howard Weiss