You may be trying to access this site from a secured browser on the server. Please enable scripts and reload this page.
Turn on more accessible mode
Turn off more accessible mode
Skip Ribbon Commands
Skip to main content
Turn off Animations
Turn on Animations
To navigate through the Ribbon, use standard browser navigation keys. To skip between groups, use Ctrl+LEFT or Ctrl+RIGHT. To jump to the first Ribbon tab use Ctrl+[. To jump to the last selected command use Ctrl+]. To activate a command, use Enter.
Browse
Tab 1 of 3.
View
Tab 2 of 3.
Page
Tab 3 of 3.
Edit
Item
Version History
Shared With
Delete Item
Manage
CCSDS.org
CWE
Areas
- SEA
- MOIMS
- CSS
- SOIS
- SLS
- SIS
Management
- CESG
- CMC
- Secretariat
- SANA
Framework
Currently selected
My Profile
Request Login
Password Management
- Change Password
- Forgot or Expired Password
Projects
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
Polling
Recent
Meeting Registration Spring 2023
Meeting Registration Spring 2020
Recycle Bin
Site contents
Manage Permissions
|
Version History
Overview
Project Title
Orbit Data Message (ODM) 5 Year Review Revision
Approval
Approved
Document Number
502.0
Charter
2.02 Navigation Working Group
Document Type
Blue
Description of Document
This project is the result of the systematic 5 Year Review of the ODM. Both retirement and reconfirmation were eliminated based on discussions at the Spring 2014 and Fall 2014 meetings. At the London Meetings in Fall 2014 the WG made the decision to revise the document based on presentations of 3 sets of recommended revisions from ESA, NASA, and the ISO TC20/SC14 representing the Space Data Association/Space Data Center.
Applicable Patents
There are no patent issues for this technology that are known by the CCSDS community
Patent Comments
No issues.
Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS
The Orbit Data Messages is one of the most infused standards developed by the CCSDS Navigation Working Group. There is no known work similar to this in other working groups inside/outside CCSDS.
Resources
Book Editor
NASA
Book Editor Resources
Prototype 1
ESA
Prototype 1 Resources
Prototype 2
NASA
Prototype 2 Resources
Prototype 3
Prototype 3 Resources
Contribute
CNES, DLR, ESA, JAXA, NASA
Monitor Only
Resource Comments
The decision to revise the document was recently made. The actual details of accepted revisions has not yet been completed. It is expected that the details of resource commitments will be filled in before the Spring 2015 meetings.
Schedule
Legend for Schedule Milestones
= Required for Orange Books
= Required for Green Books
= Required for Magenta Books
= Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books
Schedule Milestones
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project Approved
11/13/2014
11/13/2014
11/14/2014
Approved Nestor Peccia at MOIMS Closing Plenary, London.
Project Start Date
3/1/2015
3/1/2015
4/16/2015
Formal CMC Poll approval CMC-P-2015-04-002
Internal WG Review
First Draft Circulated to WG
10/1/2015
10/1/2015
3/4/2015
Work had proceeded based on verbal approval at London.
First Draft Comments Due
11/1/2015
11/1/2015
5/2/2015
Second draft circulated to WG
5/15/2016
11/30/2020
5/14/2021
P2.42 distributed
Second Draft Comments Due
6/15/2016
1/15/2021
6/14/2021
Final P2.42 comments received
Final WB Submitted to AD for Further Processing
6/30/2016
2/28/2021
6/15/2021
Submit to Mario/Marc
External Milestones
Secretariat Document Processing
8/31/2016
8/15/2021
8/30/2021
CESG Poll started 08/31/2021
First Agency Review
10/31/2016
12/14/2021
12/14/2021
Review Closed
RID Resolution
11/30/2016
1/15/2022
3/8/2022
Email to Reviewers
Secretariat Document Processing 2
1/31/2017
2/15/2022
8/30/2021
Same as 1st, no 2nd review req'd
Final Agency Review
3/31/2017
4/15/2022
12/14/2021
Same as 1st, no 2nd review req'd
RID Resolution
4/30/2017
4/30/2022
3/8/2022
Same as 1st, no 2nd review req'd
First Prototype Development
7/31/2017
6/1/2022
2/28/2022
Orekit implementation post-RID
Second Prototype Development
8/31/2017
6/30/2022
10/19/2022
COMSPOC implementation
CMC Approval
10/31/2017
4/30/2023
4/30/2023
Total Time to Complete
(in months)
31
96
Attachments
Version: 524.0
Created at 12/9/2014 5:44 PM by Berry David
Last modified at 5/5/2023 12:31 PM by Brian Oliver