Overview

Project Title

Cross Support Service Management: Simple Schedule Format Specification

Approval

Approved

Document Number

902.1

Charter

3.03 Cross Support Service Management Working Group

Document Type

Blue

Description of Document

Inter-agency schedule of space communication services data format specification.

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

Colin Haddow

Prototype 1

DLR

Prototype 1 Resources

Marcin Gnat

Prototype 2

NASA

Prototype 2 Resources

Carver Audain

Prototype 3

Prototype 3 Resources

Contribute

CNES

Monitor Only

JAXA, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet11/5/201211/5/201211/5/2013
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet11/5/201311/5/201311/5/2013
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet1/31/20131/31/20131/31/2013
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet2/28/20132/28/20132/28/2013
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet3/31/20135/1/20131/28/2014Reality is that there are more than two drafts; this refers to WG final draft
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet4/15/20133/5/20143/5/2014
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet5/31/20133/14/20143/5/2014
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet7/31/20138/29/20148/29/2014
First Agency ReviewMagenta BulletBlue Bullet9/30/201311/7/201411/7/2014
RID ResolutionMagenta BulletBlue Bullet10/31/20131/30/20151/30/2015
Secretariat Document Processing 2Magenta BulletBlue Bullet12/9/20135/2/20175/2/2017Recommendation delayed to accommodate new registry management policy
Final Agency ReviewMagenta BulletBlue Bullet1/31/20147/11/20177/11/2017No Subsequent agency reviewed deemed necessary
RID ResolutionMagenta BulletBlue Bullet2/28/20148/30/20179/19/2017
First Prototype DevelopmentBlue Bullet5/1/20133/31/20143/31/2014Prototyping was done early in development of recommendation
Second Prototype DevelopmentBlue Bullet12/1/20131/31/20171/31/2017
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/201412/8/20175/17/2018
Total Time to Complete
(in months)
4
48
Attachments
Version: 659.0
Created at 10/16/2012 5:11 PM by Barkley Erik
Last modified at 5/17/2018 7:40 PM by Erik Barkley