You may be trying to access this site from a secured browser on the server. Please enable scripts and reload this page.
Turn on more accessible mode
Turn off more accessible mode
Skip Ribbon Commands
Skip to main content
Turn off Animations
Turn on Animations
To navigate through the Ribbon, use standard browser navigation keys. To skip between groups, use Ctrl+LEFT or Ctrl+RIGHT. To jump to the first Ribbon tab use Ctrl+[. To jump to the last selected command use Ctrl+]. To activate a command, use Enter.
Browse
Tab 1 of 3.
View
Tab 2 of 3.
Page
Tab 3 of 3.
Edit
Item
Version History
Shared With
Delete Item
Manage
CCSDS.org
CWE
Areas
- SEA
- MOIMS
- CSS
- SOIS
- SLS
- SIS
Management
- CESG
- CMC
- Secretariat
- SANA
Framework
Currently selected
My Profile
Request Login
Password Management
- Change Password
- Forgot or Expired Password
Projects
It looks like your browser does not have JavaScript enabled. Please turn on JavaScript and try again.
Polling
Recent
Meeting Registration Spring 2023
Meeting Registration Spring 2020
Recycle Bin
Site contents
Manage Permissions
|
Version History
Overview
Project Title
Cross Support Service Management: Simple Schedule Format Specification
Approval
Approved
Document Number
902.1
Charter
3.03 Cross Support Service Management Working Group
Document Type
Blue
Description of Document
Inter-agency schedule of space communication services data format specification.
Applicable Patents
There are no patent issues for this technology that are known by the CCSDS community
Patent Comments
Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS
Resources
Book Editor
ESA
Book Editor Resources
Colin Haddow
Prototype 1
DLR
Prototype 1 Resources
Marcin Gnat
Prototype 2
NASA
Prototype 2 Resources
Carver Audain
Prototype 3
Prototype 3 Resources
Contribute
CNES
Monitor Only
JAXA, UKSA
Resource Comments
Schedule
Legend for Schedule Milestones
= Required for Orange Books
= Required for Green Books
= Required for Magenta Books
= Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books
Schedule Milestones
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project Approved
11/5/2012
11/5/2012
11/5/2013
Project Start Date
11/5/2013
11/5/2013
11/5/2013
Internal WG Review
First Draft Circulated to WG
1/31/2013
1/31/2013
1/31/2013
First Draft Comments Due
2/28/2013
2/28/2013
2/28/2013
Second draft circulated to WG
3/31/2013
5/1/2013
1/28/2014
Reality is that there are more than two drafts; this refers to WG final draft
Second Draft Comments Due
4/15/2013
3/5/2014
3/5/2014
Final WB Submitted to AD for Further Processing
5/31/2013
3/14/2014
3/5/2014
External Milestones
Secretariat Document Processing
7/31/2013
8/29/2014
8/29/2014
First Agency Review
9/30/2013
11/7/2014
11/7/2014
RID Resolution
10/31/2013
1/30/2015
1/30/2015
Secretariat Document Processing 2
12/9/2013
5/2/2017
5/2/2017
Recommendation delayed to accommodate new registry management policy
Final Agency Review
1/31/2014
7/11/2017
7/11/2017
No Subsequent agency reviewed deemed necessary
RID Resolution
2/28/2014
8/30/2017
9/19/2017
First Prototype Development
5/1/2013
3/31/2014
3/31/2014
Prototyping was done early in development of recommendation
Second Prototype Development
12/1/2013
1/31/2017
1/31/2017
CMC Approval
3/15/2014
12/8/2017
5/17/2018
Total Time to Complete
(in months)
4
48
Attachments
Version: 659.0
Created at 10/16/2012 5:11 PM by Barkley Erik
Last modified at 5/17/2018 7:40 PM by Erik Barkley