Revision of Proximity-1 Space Link Protocol—Physical Layer.
Projects
: Revision of Proximity-1 Space Link Protocol—Physical Layer.
Version History
Overview
Project Title
*
Revision of Proximity-1 Space Link Protocol—Physical Layer.
Document Number
211.1
Charter
*
5.01 RF and Modulation Working Group
Document Type
*
Blue Book
Description of Document
The CCSDS Recommended Standard for Proximity-1 Space Link Protocol--Data Link Layer specifies the protocol, services, and procedures pertaining to the CCSDS Version-3 Transfer Frame.
Applicable Patents
*
There are no patent issues for this technology that are known by the CCSDS community
Patent Comments
N/A
Resources
Work Group Chair Estimated Resources
Agency Volunteering
Book Editor
ESA
ESA
Prototype 1
Not Required
Not Required
Prototype 2
Not Required
Not Required
Contribute
ESA, FSA, NASA
Monitor
Schedule
Legend for Schedule Milestones
= Required for Orange Books
= Required for Green Books
= Required for Magenta Books
= Required for Blue Books
(Red Books are Draft Blue/Magenta Books)
Schedule Milestones
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Limit 255 Characters)
Project Approved
12/16/2011
12/16/2011
12/16/2011
Internal WG Review
- First draft circulated to WG
12/16/2011
12/16/2011
12/16/2011
- First draft comments due
12/16/2011
12/16/2011
12/16/2011
- Second draft circulated to WG
12/16/2011
12/16/2011
12/16/2011
- Second draft comments due
12/16/2011
12/16/2011
12/16/2011
- Final WB submitted to AD for further processing
12/19/2011
12/19/2011
12/25/2011
Secretariat Document Processing
1/31/2012
1/31/2012
3/19/2012
Agency review started on 19 March 2012, ending 1 June 2012
First Agency Review
3/31/2012
6/1/2012
3/19/2012
RID Resolution
4/30/2012
10/30/2012
10/18/2012
Secretariat Document Processing
5/30/2012
7/15/2013
Final Agency Review
7/30/2012
8/15/2013
only if needed
RID Resolution
9/30/2012
10/15/2013
only if needed
First Prototype Development
9/30/2012
10/15/2013
This review does not intruduce new features and then there is no need for protypes.
Second Prototype Development
9/30/2012
10/15/2013
This review does not intruduce new features and then there is no need for protypes.
CMC Approval
10/30/2012
12/15/2013
Total Time to Complete (in months)
10
24
Version: 45.0
Created at 12/16/2011 10:36 AM by Calzolari Gian Paolo
Last modified at 4/25/2013 5:36 AM by Calzolari Gian Paolo