Overview

Project Title

Space Data Link Security Concept of Operation, Issue 1

Approval

Approved

Document Number

350.5

Charter

5.09 Space Data Link Security WG

Document Type

Green

Description of Document

Space Data Link Security Protocol Green Book containing :
- rationale and justification of the design of the protocol
- user requirement document for the protocol
- user manual of the protocol
- mission profiles (if needed)
- discussion of performance and choice of cryptographic algorithm(s)
This green book issue 1 covers the core SDLS protocol (build-1). An issue 2 will be prepared in another project to cover in addition extended procedures of the SDLS protocol (key management, SA management, Monitoring & control) (build-2)

Applicable Patents

There are no patent issues for this technology that are known by the CCSDS community

Patent Comments

Survey of Similar Standards
Documents or Projects
Undertaken in Other Bodies
and elsewhere in CCSDS

Resources

Book Editor

ESA

Book Editor Resources

Prototype 1

Not Required

Prototype 1 Resources

Not required for Green Book.

Prototype 2

Not Required

Prototype 2 Resources

Not required for Green Book.

Prototype 3

Prototype 3 Resources

Contribute

CNES, DLR, ESA, NASA

Monitor Only

FSA, UKSA

Resource Comments

Schedule

Legend for Schedule Milestones
Orange Bullet = Required for Orange Books
Green Bullet = Required for Green Books
Magenta Bullet = Required for Magenta Books
Blue Bullet = Required for Blue Books
Note - Red Books are Draft Blue/Magenta Books

Schedule Milestones
Orange BookGreen BookMagenta BookBlue Book
Original Completion Date
(Date in M/D/YYYY format.)
Estimated Completion Date
(Date in M/D/YYYY format.)
Actual Completion Date
(Date in M/D/YYYY format.)
Comments
(Date in M/D/YYYY format.)
Project ApprovedOrange BulletGreen BulletMagenta BulletBlue Bullet11/28/200811/28/200811/28/2008
Project Start DateOrange BulletGreen BulletMagenta BulletBlue Bullet11/28/200811/28/200811/28/2008
Internal WG Review
First Draft Circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet12/15/200912/15/20093/5/2009
First Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet2/15/20102/15/20106/15/2009
Second draft circulated to WGOrange BulletGreen BulletMagenta BulletBlue Bullet3/15/20104/17/201311/1/2013
Second Draft Comments DueOrange BulletGreen BulletMagenta BulletBlue Bullet4/15/20104/15/20144/7/2014
Final WB Submitted to AD for Further ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet6/15/20103/27/20174/11/2017
External Milestones
Secretariat Document ProcessingOrange BulletGreen BulletMagenta BulletBlue Bullet9/15/20103/30/20184/30/2018
First Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
Secretariat Document Processing 2Magenta BulletBlue Bullet
Final Agency ReviewMagenta BulletBlue Bullet
RID ResolutionMagenta BulletBlue Bullet
First Prototype DevelopmentOrange BulletBlue Bullet
Second Prototype DevelopmentBlue Bullet
CMC ApprovalOrange BulletGreen BulletMagenta BulletBlue Bullet10/30/20106/21/20186/21/2018
Total Time to Complete
(in months)
23
113
Attachments
Version: 516.0
Created at 10/24/2008 12:21 PM by Moury Gilles
Last modified at 10/15/2018 11:25 AM by Gilles Moury